We first had a site shed delivered to the front of the block so that we had somewhere to stay on weekends while building. It had reverse cycle AC, beds for the 4 of us, I had a 7kVa gen set for power, an esky, a microwave and a wok, and got hold of a site toilet. What else do you need? Well that would be a list and a half. I found a small skid steer trencher with a rock chain that would do all our trenching for power water and waste except for approx. 15ft of solid granite that we hit next to the septic system. We spent from Friday arvo till Sunday evening out there doing everything I could myself, with a little help from some really good friends.
The first job was to get the access driveway and site cut done. Just had to dig up 900m3, that’s almost 1200 cubic yards. The site was split into 3 levels. The top level was for the shed, then Garage level parking, then the lower ground floor for the house.
The shed area and drive were done in two days with a D5 dozer, 5 meter scraper and a 8ft wide paw foot ********. They then started on the garage and parking level, after the next two days I had a call from the boys asking if I had any big recovery gear?????, they had ripped the tracks of the dozer and it had gone down to the culvert about 60 feet away. It took some friends of mine about 3 hours to get it back and onto the low loader. NOW what are we going to use? The local quarry is only 5 miles away so the rock here is blue! After 20 something phone calls I managed to borrow a D9H with the big tooth on the blade.
The operator arrived and asked for the layout that we wanted. I showed him the site pegs and the plans, I told him to put the outside rippers over next to the tree, his comment was “this is a D 9 H , it moves everything” so he flashed the old girl up and started to rip into it. After about 20 minutes he was over next to the tree dropping the outside rippers, then proceeded to do a 4 way cross rip with a single ripper. Now we are moving rock. He made a ramp of 45 degrees about 60 feet long, so that he had full throttle momentum to shear the rock each run he did. That is where the pool is going to go now.
The Shed was built first in 6 weeks, then the House over the last 8 years. But I have listed all the quantities together. For the footings we used a road saw to cut the rock and then an 8 ton excavator to hammer it out. This worked really well and after 8 hours all the footings were ready for prep.
The shed took 12m3 (16 yards) for the footings and the same again for the slab. The house footings took 27m3 (35 yards) and the slab 49m3 (64 yards). Then we started filling walls, for this we bought a well-used 1/2m3 (0.6 yards) mobile mixer with a single cylinder Lister engine. This is economical, it uses 9 litres ( 2 gallons) of diesel a day running from 8am until 6pm. The walls for the shed took 4.5m3 (5.8 yards) to core fill then the treated wooden trusses were thrown up and set ready for the steel roof.
After all the excavations finished we spent the next 6 weeks building the Shed every night and all weekends. We used an insulated site shed with reverse cycle AC and camp beds for Friday night to Sunday night. A portable toilet was left on site for us to use. The girls wanted this. The main focus was getting into the shed so the house was put on hold for a while.